Cleaning house!

The guys are hard at work finishing the cobble driveway for the development, and giving all the homes a good cleaning.  Its nice to see what is almost the finished product just 9 months after we started on site.  We’ve put the CGI and real photo of the detached house below, haven’t managed to get […]

Ludford Grove approaching completion

A couple of more weeks should see it done. The cobble lock is going down but as it’s laid by hand it tends to be slow. It’s looking great! Savills will be in touch with everyone who registered on a date for an open day at the site and we look forward to seeing you […]

Progress at Ludford Grove

Back patio areas are all laid, starting work on the entrance now. It will have been 8 months since construction start next week. Great progress made by the gang.

Megashowersaurus!

Master en-suite in detached home at Ludford Grove gets its oversized shower tray. Big enough for 2!

Doors, stairs & wardrobes

We’re still flat out and have a few pictures from the detached home at Ludford Grove: This is the stairs bannister rail completed in the double height hallway. The guys from Cawley’s furniture are also hard at work installing the wardrobes: And the doors have arrived and are hung, though are not painted yet. Painting […]

Kitchen complete!

The kitchen in the detached home at Ludford Grove was completed today, on time, and looks great. The worktop is maintenance free quartz, the doors and drawers solid timber with soft closing hinges. Appliances are due next week. Below you can see a picture of the utility room where there will be a full size […]

Kitchen installation underway

Nolan Kitchens have started installing the first kitchen today, with beautiful solid wood doors and a quartz worktop, it really is a top class product:

Update from Ludford Grove

With the second fix complete on the detached home (the kitchen is being tiled today), focus has moved to the semi’s where the first fix carpentry is now complete. The last set of scaffolding will be coming down next week, and we are still on track for completing the build in September.

Work Continues apace!

Work Rolls On! The recent fine weather has been a big boost.  Windows are in the first pair of semi-detached homes, and with the roof on and solar panels installed the scaffolding was finally able to come down.  Inside Number 3 (see photo below) the first fix is underway and will be completed in the […]